Duarte Sousa
Diesel – 48%
Propane – 19%
Gasoline – 60% (of 2x 5 Gal refill cans)
Water (trailer) – 80cm from the top
Water (static) – 20cm from the top
Trailer to Static Pump used - no
Water (loft) – 55
Static to Loft Pump used - yes
ATV's used: 1, 3, 4, 5, (tested 2)
Fuel Used Gals: approx 3 Gals
Hours Used Day: 30min
Notes And Comments:
Today ATV #2 was fully refuelled and tested. It seems now to be OK. Both reserve and main feeds seem to be working fine.
Summary of Engineering activities:
Engineering check, continuation of grow tent assembly.
Questions and Concerns to Mission Support:
During the EVA, one of the headsets cable got broken near the plug. It had been fixed already with tape in the past (by previous
crews), but now it's completely separated. We can try to go ahead and fix it, but the damage seems irreparable.
I checked for the possibility of having the 3-plug electrical extension at the static tank hanging upside down. The conclusion is that it is possible. Please check attached picture and let me know you opinion. An easier solution would be to cover it with plastic foil, making a cone coming from the male cable (device inside tank) and going down the female plug.
Best regards,