0118-EngineeringReport

SOL 9

ENGINEERING REPORT

Crew Engineer Name: MIKHAIL KHMELIK

Date: 18 January 2016

Diesel – 70%

Propane – 20%

Gasoline (5 Gallon containers for ATV) – 1-1/4 FULL

Water (trailer) measured in inches from the top – 15

Water (trailer) measured in inches from the bottom – 27 IN

Water (static) measured in inches from the bottom – 27 IN

Trailer to Static Pump used – NO

Water (loft) – 9

Static to Loft Pump used – YES

Water Meter: 0103532.8

Atv # Oil Checked: NO

Atv # Fuel Used Gals: NONE

Atv # Tires Status: GOOD

Atv # Hours Used Day: NONE

Atv # Notes And Comments: ALL GOOD

Summary of Engineering activities:

ENGINEERING CHECKS

Notes:

EVERYTHING LOOKS FINE FROM THE ENGINEERING CHECKS.

Questions and Concerns to Mission Support:

NONE

Requests:

NONE