Date: Dec 24th 2015
Crew Engineer Name: Chiara Cocchiara
Diesel – 30 %
Propane –51 psi
Gasoline (5 Gallon containers for ATV) – 5
Water (trailer) measured in cm from the bottom– 0 cm (full Tank)
Water (static) measured in cm from the top – 26 cm
Trailer to Static Pump used – no
Water (loft) – 10
Static to Loft Pump used – yes
Water Meter: 01025316
Atv # Oil Checked: 0
Atv # Fuel Used Gals: 1/3
Atv # Tires Status: 0
Atv # Hours Used Day: 1 Hour
Atv # Notes And Comments: 0
Summary of Engineering activities:
Everything looks fine from the Engineering Checks. We have seen that the trailer tank has been refilled. And the trash has been taken away. Thank you.
Questions and Concerns to Mission Support:
Moreover Internet has been working very badly today. We lost internet connection continuously. Even during CapCom.