Date: 04 November 2015

Crew Engineer Name: Stergios Palpanis

Diesel – 30%

Propane – 40% (gauge at the top of the tank)

Gasoline (5 Gal for ATV) – 50%

Water (trailer) – 65cm from the bottom

Water (static) – 57cm from the top

Trailer to Static Pump used - No

Water (loft) – 50 gallons

Static to Loft Pump used - Yes

Water Meter 100.300,70 Gallons on arrival (28/10/2015)

Atv # Oil Checked: Oil indicators are checked

Atv # Fuel Used Gals: 2.5 gallons

Atv # Tires Status: Good condition (arrival)

Atv # Hours Used Day: 3 Atv for half hour (familiarize using them EVA suits)

Atv # Notes And Comments: No Comments

Summary of Engineering activities:

 Last night the water pump filter, at the loft, was cleaned because it was clogged. Since we

cleaned it the sound of pump, when is working, is much less.

 Work was continued the at the deck outside the engineering airlock

 Plastic wall at the engineering lab was replaced from dry wall.