ENGINEERING REPORT SOL #7

Date: 30 Jan 2016

Crew Engineer Name: Anderson Wilder

Diesel – 50% (It’s hard to keep an accurate number because I stand so

far below the needle)

Propane – 84%

Gasoline (5 Gallon containers for ATV) – 10 Gallons

Water (trailer) measured in inches from the top– topped off

Water (static) measured in inches from the bottom – 30

Trailer to Static Pump used – No

Water (loft) – topped off early due to incoming storm

Static to Loft Pump used – No

Water Meter: 104,053.5

Atv # 3,5 Oil Checked: Good

Atv # 3,5 Fuel Used Gals: Unknown

Atv # 3,5 Tires Status: Good

Atv Hours Used Day: #3 for ~¾ for testing

Atv Notes And Comments: ATV #1 is out of commission as of right now, so

all that we have operational is ATV #3 and 5 at this moment. Pulled

battery out of #4 and charging, hopefully it’s not also dead

Summary of Engineering activities: Went through basic engineering report

procedures, everything is good

Notes: N/A

Questions and Concerns to Mission Support

N/A

REQUESTS

N/A