0303-EngineeringReport
> Engineering Report 164.11
>
> ------------------------------
--------------------------------------------------
>
> Engineering Report
>
> --------------------------------------------------------------------------------
>
> Date: 03/03/2016 at 6:30p.m.
>
>
>
> Crew Engineer Name: Louis Maller
>
>
>
> Diesel – 100%
>
>
>
> Propane – 50%
>
>
>
> Gasoline (5 Gallon containers for ATV) – one empty
> container, one
>
> half full (2.5 gallons)
>
>
>
> Water (trailer) measured in cm from the bottom– 19in
> / 42in i.e.
>
> 48cm/106.6cm from the bottom
>
>
>
> Water (static) measured in cm from the top – 25.5in / 42in
> i.e.
>
> 64.7cm/106.6cm from the top
>
>
>
> Trailer to Static Pump used – 0in i.e. 0cm
>
>
>
> Water (loft) – 51 gallons i.e. 193 liters
>
>
>
> Static to Loft Pump used – 68 gallons i.e. 257.4 liters
>
>
>
> Water Meter: 105 385.4 gallons
>
>
>
> Atv # Oil Checked: all ATVs full
>
>
>
> Atv # Fuel Used Gals: Some used, they ATVs weren’t
> refueled so we
>
> don’t know exactly how much was used
>
>
>
> Atv # Tires Status: No tire problems
>
>
>
> Atv # Hours Used Day: 1h30
>
>
>
> Atv # Notes and Comments:
>
> ATV#3 OK
>
> ATV#2 OK
>
> Red Honda OK
>
>
>
> Summary of Engineering activities:
>
> Engineering check during morning EVA.
>
>
>
> Working parts for backpack #3 put aside waiting for a
> soldering set.
>
>
>
> Questions and Concerns to Mission Support:
>
> None
>
>
>
> Cheers,
>
> Louis Maller
>
> Crew Engineer for MDRS Supaero Crew 164