328-EngineeringReport

Final Engineering Report

Date: March 28, 2015

Crew Engineer Name: Mehdi Scoubeau

Diesel – 72%

Propane – 54%

Gasoline – 12 gallons in tank

Water (trailer) – distance from top: 5cm (the trailer has been brought back) - Crew 152 has been told that from now on they have to give the distance from the bottom

Water (static) – distance from top: 55 cm

Trailer to Static Pump used - no

Water (loft) – 34 gallons

Static to Loft Pump used – yes

Water Meter (Gallons:95186.4)

Atv Oil Checked: all full

Atv Tires Status: all ok

Atv Notes And Comments: Over the two weeks, we had ATV2, 3 and 4 stalling when the engine was not warm.

Summary of Engineering activities:

- On main generator

- Internet connection via WiFi

- HALpr on

Questions and Concerns to Mission Support:

As crew 150 has already told Capcom, there is a water leak in front of the Hab. We know that it is not clean water but I just wanted to let you know that it is still leaking.

Thank you for your support and help during two weeks,

Mehdi Scoubeau