0121-EngineeringReport

SOL 12

ENGINEERING REPORT

Crew Engineer Name: MD MAHBUBUR RAHMAN

Date: 21 January 2016

Diesel – 69%

Propane – 19%

Gasoline (5 Gallon containers for ATV) – 1-1/4 FULL

Water (trailer) measured in inches from the top – 30

Water (trailer) measured in inches from the bottom – 12 IN

Water (static) measured in inches from the bottom – 34 IN

Trailer to Static Pump used – YES

Water (loft) – 9

Static to Loft Pump used – YES

Water Meter: 0103685.6

Atv # Oil Checked: NO

Atv # Fuel Used Gals: 0.3 GALLON

Atv # Tires Status: GOOD

Atv # Hours Used Day: 25 minutes

Atv # Notes And Comments: ALL GOOD

Summary of Engineering activities:

EVA, ENGINEERING CHECKS

Notes:

EVERYTHING LOOKS FINE FROM THE ENGINEERING CHECKS.

Questions and Concerns to Mission Support:

THE WATER LEVEL IN TRAILER IS GETTING LOW. WE WILL BE FINE UNTIL THE END OF OUR MISSION, BUT NEXT CREW WILL NEED IT VERY SOON.

Requests:

NONE