506-CommandersReport

Commander Report

05/06/2015

Commander crew 154

All systems except power generation nominal, crew is in a good shape.

Morning filming ni the crew quarters followed by filming in airlocks and bootom deck has been

interrupted by power outage. We received support very soon. DG switched the generators. the

primary generator may need some spare parts / may not be repairable. We are running on backup

power generator that is much more silent. So far we are not experienceing any power fluctuations.

The filming continues until now outside as simulated EVA 200 m from the hab. Hab is obviously

important landmark for the film.

We noticed that hab roof is not water tight. The roof leaks during light rain in the place of the

dining table (approximately) and the air exhaust in the roof tip is a great access for heavy

rains. It may need larger rooftip overhang.

We had two tourist visitors today from Ukraine - polite gentlemen did not interfere with our activities.

Plans for tomorrow are similar to those today - intensive filming with the whole crew from morning

till evening.

Regards