1201-EngineeringReport
--------------------------------------------------------------------------------
Engineering Report
Date: Dec 1th 2015
Crew Engineer Name: Ilaria
Diesel –70%
Propane – 78%
Gasoline (5 Gallon containers for ATV) –
Water (trailer) measured in cm from the bottom– 14 cm from the top
Water (static) measured in cm from the top – 36 cm
Trailer to Static Pump used – no
Water (loft) – 9
Static to Loft Pump used - no
Water Meter:
Atv # Oil Checked:
Atv # Fuel Used Gals:
Atv # Tires Status:
Atv # Hours Used Day:
Atv # Notes And Comments:
Summary of Engineering activities:
· The ground floor and the toilets are incredible clear and shining.
· The new rule (i.e. plastic bag for number 2) is working well!
· There are no gators for EVA.
· The back pack number 6 is not working because the clicking switch (not the flat switch) can hold the on position. The ventilation is on only if you keep pressing the switch in the on positon.
· No hot water. I am going to follow Paul’s suggestions and fix it tomorrow.
· One of the five headphones is not working.
Questions and Concerns to Mission Support:
· The bag packs (1,2,3 and 4) for EVA are working and now are charging. Is there any tool to measure the charge of each? Cannot find any tool both in the EVA room and in the engineering side.