0331-EngineeringReport
Hey Mission Support, here's the report:
Date: 03/31/2016 at 6:45p.m.
Crew Engineer Name: Gregory Edison
Diesel – 50%
Propane – 36%
Gasoline (5 Gallon containers for ATV) – 1 full container, 1 half
full container
Water (trailer) measured in cm from the bottom – 28in / 42in
Water (static) measured in cm from the bottom – 26.5in / 42in
Trailer to Static Pump used – No
Water (loft) – 50 gallons
Static to Loft Pump used – 35 gallons
Water Meter: 106774,9 gallons
Summary of Engineering activities: Routine check, filled the ATV's with gas.
Questions and Concerns to Mission Support:
Power: Still on Cat. It appears oil leak has been fixed. No oil added.
Tomorrow we will run it all day (no check at 5 pm) but I will check it
again on Saturday at 5 pm. Main generator needs a new head. It has been
ordered but will ship as freight so it will take some time to get here.